Wednesday 13 May 2015

Parent meeting with Golder Associates

Notes provided by Jodie Terry from the meeting with Golders on 12th May. 

These are not minutes and so have not been agreed by participants - they are personal notes and may therefore be subject to misinterpretation or inaccuracy. They are intended to give a general summary of what was discussed. More detailed information will be available when the presentations including answers to specific questions are loaded to the website.

The meeting was attended by about 25 parents as well as representatives from Golder Associates, Soilfix, ECHarris, RBKC and Fox.

Works will commence the week starting 18th May.
During the first week the wall along side the school, on Kensington place will be removed and replaced with temporary hoarding. A portable building will be installed providing children’s toilets and school office. These toilets are not ‘portaloos’ but proper plumbed in toilets. These will be in place for the entire project. The contractor compound will be established for the enabling works contractor, cordoned off from the rest of school with high hoarding. During the week of the 18th May the north playground will not be open to children.
During half term the cottage will be removed. First, all items containing lead will be removed by hand and contained in covered skips. Following this the rest of the cottage will be demolished carefully using controlled demolition methods and removed from site. Also during this week the most of the elements within the toilet block which have evidence of contamination will be removed by hand and contained in covered skips.
In the first week after half term (week commencing 1st June) the toilet block connecting the school building to the embankment will be removed. This building has fewer items containing high levels of lead. The remaining contaminated elements that it was not possible to remove during the half term will be removed by hand under controlled conditions and contained.
These works will be done behind high hoarding with stringent dust containment methods in place.
Also during the week starting 1st June, the sanitary connections will be made to the temporary toilets and utilities will be connected to the temporary office.
Access to the eastern end (about 50%) of the north playground will be restored in the week starting 8th June and the toilets and temporary office will be in use.
Dependent on the type of work being done there will be regular air monitoring to check that dust levels are maintained below safe limits. At higher risk times this will be done daily. These readings will be shared with the school as soon as possible.
Prior to any demolition there will be swabs done of the school environment to establish a baseline reading. During and after the demolition these swabs will be repeated and compared to the baseline, to ensure that dust containment is working and therefore contaminants are not being released.
Golder have requested an estimated turnaround time from the lab analysing these swabs and hopes that they will be able to do them within 24 hours but cannot yet confirm that. The results of analysis will be made available on the school website. 

The Health and Safety Executive has approved the methodology being used for these works.

Weekly updates on building progress will be provided by the school in the Newsletter. 