Thursday, 5 February 2015

Building Meeting

5th February
PC, KP, JT and GD met with EC Harris, Soilfix and Golders to discuss the removal of the raised beds in the playground in advance of building work. Contamination at 'undetectable levels' but will still need to be removed under controlled conditions. Majority of raised bed soil to be removed over half term. Soilfix will present to parents about the methodology for removing contaminated soil on the 12th February. For compliance reasons nothing other than memorial plants (after testing) to be retained.